Fermoy, Co. Cork
- Duration: Two weeks
52no. Piles 450mm diameter installed at 600mm centres to allow for the site to be excavated.
The piles were installed from a temporary platform created for our 14T Tescar CF3 rig. On completion of the piling a capping beam was installed, the site was then excavated to the required level and faced with a reinforced concrete retaining wall.